Cost headShareWhat sits inside
Structure & RCC28%Steel, cement, aggregates, shuttering and the frame the asset stands on.
Envelope & facade16%Blockwork, plaster, glazing, cladding and weatherproofing.
MEP services19%HT/LT electricals, HVAC, plumbing, fire fighting and detection.
Vertical transport7%Lifts, escalators, shafts and machine-room provisions.
Finishes15%Flooring, ceilings, joinery, paint and washroom fit-out.
External works8%Parking, ramps, drainage, compound, landscape and signage.
Statutory & approvals4%Planning permission, fire NOC, EB sanction, lift licence, OC.